Fountain Square in Piégros-La-Clastre
Technical informations
Project owner
Commune of Piégros-la-Clastre (26)
Team
SMall Paysagiste lead contractor, Florent Rougemont architect, STADIA for VRD and hydraulic infrastructure
Mission
Studies for all phases including ESQ/APS/APD/PRO up to the operational construction phase
Landscaping component
Urban and landscape design of the village central square : modification of the crossing road, movement of parking spaces outside the square in favor of a pedestrian space conducive to village life, partial felling of diseased plane trees, creation of planted pockets of perennials at the base of the new trees, enhancement of the fountain, memorials to the dead and church square by the retreat of the wall of the old mill of approximately 7.00 meters of newly acquired clearance, consultation work with the residents
Budget
€650K excl. tax
Area
3500m²
Date
Ongoing studies in 2024